Scope of Work

1
Fabricate and install metal stairs A,B,C,D

Included: metal stringers ,precast full riser concrete treads, mid landings (concrete by others), stair rails, wall/rail mount grab rails, cane detector rails (including landing pipe risers), Stair C decorative stair rails,enginireering Excluding treads protection , submit drawings to the City

$778,980.00
2
Fabricate and install Roof access ladders at stair A

Qty 1 ea. Primer only. Excludes safety rails around roof hatch

$1,850.00
3
Fabricate and install interior ramps 1 and 2

Primer only

$7,280.00
4
Fabricate and install non bearing masonry wall attachment

Approx. 100 ea. ,per 2/S006

$12,000.00
5
Fabricate and install steel for double elevator

Includes: 42 ea. guide rail plates ,Qty- 4 ea. hoist beams, Qty-2 ea. pit ladders, Qty-11 divider beams , separation screen All steel per structural Ecludes HSS tubings for guide rails

$42,276.00
6
Fabricate and install metal frames for glass railings

Glass by others,Hot dipped galvanized (HDG) , Powder coated Providing channel for glass

$219,672.00
7
Fabricate and install decorative picket metal railings

Powder coated ,Budget only Excludes galvanizing

$451,948.00
8
Fabricate and install metal railings with perforated panels

Powder coated,Budget only Excludes galvanizing

$125,425.00
9
Fabricate and install ground floor patio fence and gates

per 9/A502 , Powder coated, 6' tall, Qty-4 ea. gates Excludes galvanizing

$24,996.00
10
Fabricate and install Juliette rails

per 4/A502, Powder coated,Qty-3 ea. Excludes galvanizing

$5,952.00
11
Fabricate and install balcony separations

per 3/A502, Powder coated , 6' tall, Qty-40 ea. Excludes galvanizing

$90,050.00
12
Fabricate and install roof screens around boilers

per 1/A521, qty-4 ea. gates, 4' tall ,HDG Powder coated ,Backing by others, Excludes wood planks

$47,900.00
13
Fabricate and install bollards, and garage pipe guards

Budget only, unknown Qty

$16,400.00
14
Fabricate and install overhead door support steel at garage

Budget only , unknown design

$9,600.00
Proposal Total$1,834,329.00

Exclusions

  1. 1.Any concrete work
  2. 2.Permit fees
  3. 3.Finish paint
  4. 4.Metalizing (galvanizing, zinc spray, etc.) unless specified
  5. 5.Cost of field inspection (welding, epoxy anchors, etc.)
  6. 6.Any plan submittals to the City
  7. 7.Items not included in this proposal
  8. 8.Demolition and disposal of any items
  9. 9.All exclusions provided in breakdown
  10. 10.Scaffolding
  11. 11.Gate hardware, openers and self closures unless specified
  12. 12.Roofing materials such as foam, roofing, waterproofing and flashing
  13. 13.Engineering unless specified
  14. 14.Powder coating unless specified
  15. 15.Detail 4/A580 -----unknown design
  16. 16.Chainlink fence
  17. 17.From landscaping keynote #22 Overhead at BBQ--- unknown design
  18. 18.From landscaping keynote 26 Custom cabanas at pool----unknown design
  19. 19.From landscaping keynote #28 Pool gate frame------unknown design
  20. 20.Low roof trelliss per 4/A451
  21. 21.Storefront columns and beams per 2,3/S009